PROPOSAL FOR A MULTIPURPOSE PROJECT
ON THE RIVER   KHOWAI
S.CHOWDHURY
B.E, C.Eng. F.I.E.


Out of seven Major rivers in Tripura namely Howrah, Khowai, Dhalai, Manu, Deo, Gumti and Muhari, only the river Gumti has been harnessed and a 2 ×5 MW Hydro Electric PowerStation has been commissioned on the same during 1976 at Tirthamukh. A concrete Dam was constructed at 2.5Km up stream of the Power House for creating a reservoir of 45sq. Km. area (approx) which has also been gainfully utilized by the Fishery Deptt. For fishy-culture. The Hydel power station at Gumti is operating smoothly and 8.5 MW power is being generated by two units, the 3rd one   commissioned during1990 being stand-by. The energy available is 60- Million units per annum at very nominal cost of generation from Gumti Hydel Project.
During mid 80’s at down stream of the river Gumti an Irrigation barrage has been constructed at Maharani with the regulated tail water discharge of 800-1000 cusec round the clock covered 1250 Hector of paddy land may be extended upto 4486 Hector, the target command area in the DPR. The irrigation facility thus created has boosted up growth in Agri-sector substantially. Apart from that the flood moderation at down stream under Udaipur and Amarpur sub-Division has been achieved subsequent to the construction of the Dam.

KHOWAI RIVER -The second prospective proposal is on the river Khowai which could be tried for gainful utilization.

Incidently an Irrigation barrage has already been constructed by the I&FC Deptt. at Chakmaghat on Khowai river now in operation for couple of years. The barrage has two irrigation cannel one on right bank and another on left bank, having requirement of 80+75 =155 cusecs in total. However during rainy season the gate of barrage are kept open since the high flow discharge of Khowai in more than 60,000 cusec which cannot be hold by the barrage as a result substantial quantum water flows  to Bay of Bengal through Bangladesh unutilized.

For gainful utilization of the water of Khowai river, a multipurpose scheme for fishery, Duckery, Irrigation,(already existing partly) ,flood moderation and Power generation etc. could be thought for.

In fact Central Water Commission (CWC) made a survey of all Major rivers in this area and in specific the Khowai River during mid 80’s.They proposed for a multipurpose project as stated above and Generation of power was a component of the total scheme.

In the report CWC proposed for construction of a rock-filled earthen dam at 3 Km upstream of the existing barrage at Chakmaghat on the river Khowai.This will create a reservoir for storing the water of khowai river at the upstream including the high flood discharge which will be helpful for flood moderation at downstream at kalyanpur, khowai etc.Apart from that such a large storage of 52,112 ha. meter would be enough for fishery, duckery etc for the concerned Deptts. under Govt. of Tripura for their development schemes for its gainful utilization.

Power Generation: In the design part for power generation, CWC considered the tail water discharge level of the Hydel Power house 2 meter above the maximum pondage level of the barrage. The height of dam was kept purposely lower to minimize the submersion of paddy land, property submersion and eviction of people of neighboring localities. With these precautions, it is seen that a firm power of 3.90 MW only is available with the live storage of 47,862 ha.m. with average head of 32.85M and a regulated discharge of 15.18 cumecs from the river Khowai. Incase we go for 25% Load factor (LF) 15.61 MW power could be generated by 2x10 MW units during peak load Hours to supplement the shortage of peak power demand during evening i.e. from 5 Pm to 11 Pm every day.  Alternately with 40% LF the power availability is 10 MW only which can be generated by 2X5 MW units. In addition, with the regulated tail water discharge of 15.18 cumecs (536 cusec), another Irrigation Barrage scheme at Kalyanpur at down stream of Chakmaghat seems feasible which will be an added benefit in Agri- Sector.

Of course CWC in their report has mentioned that about 779 families are to resettled elsewhere for which cost shall be an in built component to the project estimate.

The present Peak demand of the State is 150MW (5PM to 10PM) and at off peak hour it reduces to 70MW in winter. This figure touches 160Mw in peak and 70-80 MW in off Peak hours in summer. Therefore the short fall is mostly during Peak- Load hours which can not be meet with own generation of the state but the off-peak demand could be meet with our own generation of 70MW now available, e.g. at Baramura 21 MW Rokhia 40MW and Gumti Project 8.5MW.

Therefore the firm Power of 3.9MW as could be made available from the proposed Khowai DAM Project is less useful during off peak hours but if the same water could be utilized for 6 hours every day, i.e. from 5pm to 11PM Peak generation of 15-16MW in the evening helps substantially to reduce the peak power shortage.

The salient   feature of the scheme is reproduced below:-

 

TENTATIVE SAILENT FEATURES OF THE proposed KHOWAL DAM AT 3 KM UP STREAM OF CHAKMAGHAT BARRAGE.

I. Location

            State                                                    Tripura

            District                                                 Tripura (west)

            River                                                    Khowai

            Dam Site                                              9 k.m. upstream of Teliamura

II.  Hydrology

Catchment area                                    500 sq. km.

Normal annual rainfall                           1,058 mm

Dependable yield           90%                47,862 ha.m

75%                50,276 ha.m

50%                56,774 ha.m

Design flood                                        1727 Cumces

 

III. Reservoir

Gross storage                                      52,112 ha.m

Live storage                                         47,862 ha.m

 

IV.  Dam Type                                         Earthen dam

Bed level                                             46.9 m

Top of dam                                          90.0 m

Height of dam                                      43.1 m

Free board                                           3.2 m

Average Head available                         32.85 m

 

V.     Spillway

Type                                                    Saddle spillway

 

VI.  Power

Average water flow                              15.18 cumece

Output-Firm Power                              3.90MW

Peak power at 25% L.F.                      15.61MW

  T he project site for construction of the Dam and the Power House at the foot of the Dam is within one Km from NH44 as such transportation of construction material will be easy. With present price index the project could be implemented @ 7.00 core / MW including all charges. The length of HV Transmission line required is only 10Km to connect the Khowai Hydel Power station at 66 KV with Teliamura 66KV Sub-station. Other infrastructural facilities are like Hospital, School, Market; Bank etc. are already   available at Teliamura as a result the cost per MW of installed capacity will be reduced proportionately.

The scheme falls under Re-newable Energy Category as such Ministry of Non-conventional Energy Sources of Govt. of INDIA would like to provide the funds as 90% grant as Micro-Hydel Project for NE-Region.

The estimated cost of generation is Rs 2.21 / KWHr.(approx) Which is reasonable with 2x10 MW Hydel unit .The annual energy generation will be around 35-40 million Unit( MU) (approx). Since no fuel is burnt it will not pollute the environment. By adding this peaking station of 2x10 MW capacities in the system, the state could have assured peak power assistance under his own control to meet the peak-short fall partly. It will save cost of import of power over Rs.9.00 cores per annuam considering average of cost of import @ Rs.2.5 /unit. This power could be utilized during emergency period when 132KVA line connection NE Grid is out of order or the external power is not temporarily available for some reason.

Apart from that by sale of power to be generated to our consumers, revenue of equal amount could be collected to boost up our income for the Power Deptt.

  Calculation for cost of generation of Khowai Hydro Electric Project (2X10MW

SL No.                  DESCRIPTION                                          AMOUNT

1          Total project cost of 2x10MW @ Rs.7.00/MW           Rs.140core

2.         Under MNES for Micro Hydels

grant 90%on Rs.140core                                         Rs 126 core

3.         10% Loan with interest on Rs.140core                      Rs.14.00core

4.         Interest on loan @ 12 %on Rs 14.00core                  Rs.1.68 core

5.         Depreciation @ 2.25% considering

40 years life of project on total 126

core keeping 10% reserve value                               Rs.2.84 core

6.                  Operation & Mtc.@ 2.5%

i/c establishment on Rs 140 core                            Rs.3.50 core

7.         Total annual fixed charge Adding (Sl no.4+5+6)        Rs.8.02 core

8.         Total unit available in Million Units                                37.5 MU

9.         Cost of generation at HT Bus                                        Rs.2.14

10.       Add 3.5 % profit                                                          Rs.0.07

11.       Cost of salable power at HT Bus                                  Rs.2.21 per kwhr.***
Which seems to be reasonable compared to the cost of import of power from Central  Sector Power stations of N E Region.

Alternative proposal for 2X5MW-units

In case we go for 40% L.F. 2X5 MW units could be installed restricting the peak power availability upto 10 MW only, with Rs, 70 cores as total cost of the project. The cost of generation will be reduced substantially with the reduction of plant size and investment as calculated below:-

Calculation for cost of generation of Khowai Hydro Electric Project (2X5MW)

SL No.              DESCRIPTION                                             Amount

1          Total project cost of 2x5MW @ Rs.7.00/MW           Rs.70core

2.         Under MNES for Micro Hydels

grant 90%on Rs.70core                                         Rs 63.00 core

3.         10% Loan with interest on Rs.70.0core                   Rs.7.00 core

4.         Interest on loan @ 12 %on Rs 7.00core                  Rs.0.84 core

5.         Depreciation @ 2.25% considering

40 years life of project on total 63

core keeping 10% reserve value                             Rs.1.42 core

7.          Operation & Mtc.@ 2.5%

i/c establishment on Rs 70 core                             Rs.1.75 core

7.         Total annual fixed charge Adding (Sl no.4+5+6)       Rs.4.01 core

8.         Total unit available in Million Units                           37.5 MU

9.         Cost of generation at HT Bus                                  Rs.1.068

10.       Add 3.5 % profit                                                     Rs.0.0374

11.       Cost of salable power at HT Bus                          Rs.1.17 per kwhr. ***

*** In case the cost creation of the RESERVOIR is shared proportionately by I&FC, ARDD and FISHERY Depts. deriving benefit from reservoir to be created the cost of generation of will be reduced to a greater extent.

The above summary of the scheme deserves consideration by the authority for detail investigation and study by the respective Deptts. for implementation for the multipurpose project on irrigation and flood moderation, fishery, duckery  and power generation on the river KHOWAI for the development of the state.